Undertaking a cost-to-complete exercise on a major incomplete teaching and research hospital
Brief
HKA was engaged to undertake a cost-to-complete exercise on the incomplete teaching and research hospital. The detailed analysis required a collaborative approach by our building services engineers, quantum and delay consultants, who were based on site for a number of weeks.
Following an analysis of the findings, HKA acted as independent moderator to calculate termination compensation in accordance with the terms of the project surety bonds.
What we did
HKA’s building services engineers worked closely with mechanical, electrical and plumbing (MEP) sub-contractors engaged on the project in order to understand the status of works completed, what remained to be completed, and any other associated risks to time and/or budget.
Drawing on the findings of HKA’s technical experts, our delay and quantum specialists assessed the reasonable forecast completion date and final costs to complete the project.
Outcomes
HKA’s assessment under the surety bonds was accepted in full. The thoroughness of the analysis meant that the conclusions were not subject to challenge or further scrutiny by the bond providers own assessors.

-
ClientConfidential
-
Year2018
-
ValueUS$327million
-
ServicesQuantum, Engineering, Architecture & Technical, Delay
-
SectorsBuildings
RELATED PROJECTS
RELATED PROJECTS

Two New Venues
Middle East

New School Campus, Ultimo Primary School
Oceania

UNSW Capital Projects Sustainability Framework
Oceania

Residential Development
Middle East

University of North Carolina Hospitals
Americas

Share our Space Program
Oceania

Hume Community Housing
Oceania

Temporary School at Ultimo Primary School
Oceania

Office and Retail Landmark
Americas
Follow HKA on WeChat
关注我们的官方微信公众号
