Technical Interview

From Vision to Reality with Tim Whealy

As published by Middle East Consultant – November/December 2025 Issue

HKA’s Tim Whealy, Partner, talks to MEC’s Jason Saundalkar about HKA’s business in Saudi Arabia and why the various players in the construction supply chain must adjust their thinking to avoid existing and new project design and delivery issues.

UK-headquartered HKA has decades of experience in Saudi Arabia and in early 2024, the global consultancy strengthened its commitment to the Kingdom by securing its Regional Headquarters (RHQ) License. The move positioned HKA as amongst the first major international consultancies to gain regional HQ status under the programme, enabling the firm to conduct business with Saudi state bodies and benefit from certain tax incentives.

Even prior to acquiring RHQ status, HKA already had strong ties to the Kingdom, with its Riyadh and Jeddah offices supporting Saudi clients and capital projects for over two decades. Talking to Jason Saundalkar, Head of Content at Middle East Consultant, Tim Whealy, Partner at HKA said that today the firm continues to deliver services to a variety of clients, and notes that the company’s business has grown, and evolved, since it opened its RHQ.

Over the 2024-2025 period, the Kingdom continued working on diversifying its economy away from hydrocarbons in line with the goals of Saudi Vision 2030. Since Vision 2030 was unveiled over a decade ago, the country has had a number of successes in terms of its overall transformation, and the delivery of components that are a part of its various giga projects, including: the completion of the initial phase of NEOM Bay Airport; the partial opening of Diriyah Gate; the opening of a significant portion of the King Abdullah Financial District (KAFD); the opening of a number of the Red Sea Project’s resorts and many others.

Over the last 12-18 months, the Kingdom seems to have kicked off a sharper focus on completing certain key giga projects. While this has slowed contract awards and work on some of the Kingdom’s giga projects, development is continuing in earnest on others. According to a recent Knight Frank report, in the first eight months of 2025 alone, US$3.7bn in contracts were awarded for the Diriyah Gate project. This move follows the $5.9bn in contracts awarded on the project in 2024.

Whealy first began working in the Kingdom in 2011 and notes that the perception of the country at that time was that it was a hardship posting. Today, the situation is far different, he notes.

Delivering Vision 2030

Since Vision 2030 was first unveiled, Saudi Arabia has made tremendous progress on its transformation journey, even looking outside of the delivery of its various giga projects. Post 2020, the country secured the rights to host Expo 2030 Riyadh and the 2034 FIFA World Cup – two significant mega events that will support the Kingdom’s transformation journey and help the government positively shift the country’s perception on the world stage.

The successful delivery of those events is connected with the upgrade of existing assets, and the design and completion of all new assets and infrastructure in line with the original vision. It’s therefore vital that employers and construction industry stakeholders change the way they approach projects, and the way they interact with each other.

A change of mindset

According to HKA’s Eighth Annual CRUX Insight Report, which analysed more than 2,200 projects in 114 countries with a combined CAPEX of $2.43tn, projects in the Middle East have faced the longest schedule overruns. The top five causes of claims or dispute in the region were due to: change in scope; the late issue of design information; cash flow and payment issues; late approvals, and incomplete design.

Asked about the Saudi market in terms of contract structure and the way project stakeholders work with each other following the unveiling of Vision 2030 in 2016, Whealy notes that historic challenges continue to persist, and must be addressed.

Here, Whealy says contractors also play a role in the country’s project challenges and should shift their thinking to ensure the best outcomes for themselves and the projects they deliver.

Highlighting another challenge that companies must consider are the implications of price escalation. Whealy says there’s been significant price escalation in Saudi but yet companies are reluctant to put price escalation provisions into their planning.

Delving deeper into the relationships project stakeholders have, specifically with regards to consultants and contractors, Whealy says that a combative mindset is the norm.

Sharing an example of how current contracts and mindsets jeopardise projects, Whealy says that a contractor was recently looking to unilaterally terminate a contract because they couldn’t afford to remain on the project, and if that happened, it would have significant ramifications on the project and the employer. “There are very real implications of the current approach that are never fully considered,” he reiterates.

Making his closing statements, Whealy notes that the Kingdom has embarked on one of the biggest and most ambitious national rebuilding projects in his lifetime, and says that the rate of change has already been “phenomenal.”

Having said that, Whealy says there is a place for collaborative contracting and says that while it doesn’t work on every project, it can have a positive impact, but it requires a fundamental change in mindset to make it work.

He concludes, “There has to be an acceptance from people to finding common solutions rather than following the normal play book where the parties retreat to their respective sides and play the blame game. There are other forms of procurement that can be tried, but I’m not sure that the Saudi market is ready for management forms of contract and other approaches that give clients a lot more opportunity to change and control. As a start, I think the best thing employers can do is go slow to go fast. This means getting the design right, stress testing it to make sure everything works, ensuring that they really are at that particular point in the design process, and then making an informed decision to move forward on their projects with the right construction partners.”

Tim Whealy (timwhealy@hka.com) is a Chartered Quantity Surveyor with over 25 years of experience in the construction industry. He supports clients regarding commercial and claims matters, provides lender’s advisory services, and has acted as quantum expert on many occasions (including cross-examination in court).


This publication presents the views, thoughts or opinions of the author and not necessarily those of HKA. Whilst we take every care to ensure the accuracy of this information at the time of publication, the content is not intended to deal with all aspects of the subject referred to, should not be relied upon and does not constitute advice of any kind. This publication is protected by copyright © 2026 HKA Global Ltd.

X

Follow HKA on WeChat

关注我们的官方微信公众号

HKA WeChat